CA: (209) 745-7400 | NV: (775) 312-6229

Citrus Heights City Hall ‘on target’ to be completed by September

Construction of the new $22 million Citrus Heights city hall is “on target” for completion by September of this year, according to the project’s manager and City officials.

After beginning work on the project last July, Project Manager Tyler Gahagan said structural steel went in earlier this month, followed by a roof being put on the 35,000-square-foot facility last week. Currently, he said crews have started metal stud framing and are installing plumbing and electrical. Read More...

Concrete North, Inc. began working on the Tilt-Up Concrete Construction in August 2015 and anticipates to start the Site Concrete / Reinforcing soon with an estimated project completion April 2016. Concrete North is contracted under Ascent Builders, Inc.

Print Friendly, PDF & Email

No Comments Yet.

Leave a comment